An MRI Room Needed a Florida Seal. Who Signs the Shielding?
The request landed on the shielding company first. A general contractor building out an MRI suite for a radiology clinic in Lehigh Acres asked the company that makes the room's shielding to digitally sign and seal its drawings. The drawings had to go to the building department with the permit submittal, and the permit expediter required a seal.
The shielding company is based out of state. The contractor's project manager put it plainly in an email to the team: the company had never done this before. Not everyone on the project team was sure the requirement even applied to MRI shielding drawings.
A few days later the shielding company's project manager called us, then emailed over the project drawings. That is how we ended up on an MRI job.
What the shielding actually is
An MRI scanner listens for very faint radio signals from the body. Outside radio noise would spoil the images. So the scan room is lined with RF shielding (radio-frequency shielding: a metal-lined room that keeps those outside signals out). On this job the shielding company reported panels of about 4.5 pounds per square foot, lining the floor, the walls and the ceiling.
Two parts of that system are structural questions, not radio questions:
The shielded ceiling hangs from the building. It is suspended on hangers from the structure above, which on this building is the roof framing over the scan room.
The vent goes through the roof. An MRI magnet has a cryogen vent, the pipe that lets the magnet's helium escape safely to the outside. It runs up through a curb on the roof and stands above the roof, where it takes Florida wind like anything else up there.
The shielding company makes the shielding and answers for how well it blocks radio signals. How that shielding hangs from a particular Florida building, and how the vent holds up in Florida wind, is engineering for that building.
What we did
The permit expediter explained to the team that shop drawings involving engineered design or structural integrity go to the building department signed and sealed by a Florida-licensed professional. In practice that is often a delegated engineer, an engineer who designs one part of a building, such as trusses or a component like this, while the building's own engineer of record stays responsible for the building.
Our agreement was signed on October 30. The same day, the contractor asked when the signed and sealed copy would be ready, so they could file. Our answer listed what we needed before the engineering could start:
The weights of the shielding and the ceiling hanger layout. The shielding drawings showed the plate layout but no weights.
The existing roof framing above the scan room: the truss shop drawings, or a truss layout with spacing and member sizes.
The roof curb at the vent: its size, height and construction, and the roof height there.
The weights and the hanger layout came in on November 2, and the signed and sealed structural set followed: three sheets that go with the shielding company's drawings. They cover how the shielded ceiling hangs from the structure above the scan room and the cryogen vent above the roof, with a table of the loads for the building's engineer. The digital seal was applied with markups allowed, so the expediter could add an approval stamp without breaking it, and the contractor had what it needed to file.
What to do if you are building out a medical suite
Ask about seals early. When an equipment or specialty vendor's drawings go in with your permit, ask the vendor in the first week whether a Florida-licensed engineer will seal them. Out-of-state companies may not have been asked before.
Get the weights in writing. Shielding, equipment, hung ceilings and anything else that hangs from the structure. Weights are the first thing the engineer needs.
Find the roof framing documents. Truss shop drawings or the truss layout for the area above the room. If nobody has them, plan for someone to verify them in the field.
Know who checks the building. The building's engineer of record checks whether the existing structure can carry the new loads. Make sure that engineer gets the load table.
Do not cut the trusses. A hanger, duct or pipe in the way can tempt someone to cut one. Ask first.
Ask for markups allowed. If your expediter stamps the drawings, ask for the digital signature to allow markups so the stamp does not break the seal.
Frequently asked questions
Does every vendor drawing need a Florida engineer's seal?
Not every one. Drawings that involve engineered design or structural integrity, such as how something heavy hangs from the building or how a rooftop item holds in the wind, generally do. Your permit expediter or building department can tell you what they will accept for your job.
Can the vendor's own engineer in another state sign them?
On this job, the permit expediter required the seal of a Florida-licensed engineer. Ask early whether the vendor has one or will hire one.
Do you work on commercial buildings?
Yes. This MRI suite is one example, and we work on commercial buildings in Fort Myers and Cape Coral. We offer unmatched turnaround times, and 5-7 day rush turnaround is available upon request for a premium fee.
Have vendor drawings that need a Florida engineer? Contact us or call 239-292-7670.